 |
Renewable
Energy and
Co-Generation continued
Ergon
Energy - Isis Central Sugar Mill Co-Generation Power Station (Childers,
Queensland)
The decision to
undertake the entire project was prompted not only by the success of
similar generation control projects within various industries (as outlined
below), but by the confidence that we had the right expertise within
our Projects & Construction team to undertake a project of this
size, further involving mechanical and electrical disciplines, and construction
and project management.
i.power solutions
role as Principal Contractor encompassed the design, manufacture, supply,
procurement, erection, installation and commissioning of the entire
project, utilizing some major items of free issue equipment:
- 25MW steam
turbine, gearbox, generator and condenser
- Forced-draft,
6-cell mechanical cooling tower
- Cooling
water pumps and all water and steam pipe reticulation
- Turbine
building complete with 10-tonne overhead crane
- Switchrooms
including 415V motor control centre and 11kV switchboard
- Entire
control and monitoring systems including governing and excitation
systems
- Station
services, earthing and interconnecting transformers
- Civil construction
works including bulk earthworks and land reclamation, piling
and foundations for all plant and the 11/66kV grid connection
switchyard
- All electrical
and mechanical design including 3-D modeling of cooling tower,
turbine-generator assembly, piping and equipment.
|
 |

 |
FACTS
- The power
plant will use excess steam produced through the combustion
of sugar cane residue (bagasse) at the Isis Mill to drive its
power turbine and has been designed and constructed with due
consideration to reliability, the latest technology and environmental
management.
- When utilised
to full capacity, the plant is expected to generate about 65,000MWh
of green energy in a season. With 30% used to run the sugar
mill, the remainder when exported to the QLD electricity grid
will be sufficient to power 7,000 homes as well as improve the
reliability and quality of electricity supply to Childers and
surrounding areas.
- The new
plant is expected to help reduce greenhouse gas emissions by
up to 50,000 tonnes every year; equivalent to taking more than
10,000 cars off the road.
- The Isis
Co-Generation Power Station was completed on time in June 2006,
with no disruption to mill startup.
|

Back
to Renewable Energy
|
|